×
Register Here to Apply for Jobs or Post Jobs. X

Electrician

Job in Columbus, Franklin County, Ohio, 43224, USA
Listing for: Fusion Solutions, LLC
Full Time position
Listed on 2026-06-13
Job specializations:
  • Trades / Skilled Labor
    Installation Technician, Electrician/ Electrician Installation, General Labor, Field/Service Technician
Salary/Wage Range or Industry Benchmark: 60000 - 80000 USD Yearly USD 60000.00 80000.00 YEAR
Job Description & How to Apply Below

Fusion Solutions is looking for a team of electricians to install and commission conveyor belts in Radnor, OH and West Jefferson, OH. Details listed below. Please let me know a good time to connect if interested. Feel free to send me a copy of your resume at M or call at:

Title:

Journeyman and 2 – 3 Certified Electrician

Location:

Radnor, OH and West Jefferson OH

Work Done at a Staging Sites in Radnor and then commissioning done in West Jefferson after a week or two

1 week: 4 – 5 days at staging sites / testing

And then 2-3 days for commissioning on Site in West Jefferson

Start:
Mid-June 3, 2026

Duration: 1 month project

Job Description
  • The contractor shall wire all equipment in accordance with the attached drawing set. All wires and cables
  • shall be properly identified at all termination points.
  • The contractor shall supply all wire, conduits, connectors, terminal blocks, hole seals, pull boxes,
  • and other equipment required for complete installation unless otherwise stated in this document.
  • All wire terminations shall be made by the contractor in a neat and professional manner that is acceptable to our company.
  • A maximum connection of two wires per terminal screw.
  • Ring type crimp lugs shall be used for wires greater than 110V when the equipment supports it.
  • Wire number labels shall be applied to all wires at each end. If part of a multiconductor cable set the cable shall be labeled at each end.
  • All terminations should follow the schematics and labeling conventions.
  • Wire labels shall be adhesive self-laminating wrap around. Wire numbers shall be legible from all sides.
  • Label Devices in the field consult our associate on-site for label positioning.
  • Any deviations from the electrical installation documents provided must be approved by the engineer prior to use.
  • All work areas must be kept clean.
  • The contractor shall install all conduit, wire, and cable in accordance with the 2023 NEC and our company standards.
Install for FAT – Radnor, OH
  • See pull schedule for cable routing, cable labeling, and wire labeling
    • Mount Sensors
    • Sensors and Valves will be terminated with single ended cord set M12 to Flying Leads
    • Route and terminate cables from I/O to Junction Boxes
      • Photo-eyes, Proximity Sensors, Reed Switches, Valves, etc.
    • Route and terminate cables from I/O to the Operator Panel
      • Photo-eyes, Proximity Sensors, Reed Switches, Valves, etc.
      • Key Switch 1
      • Gate Switch 1
    • Route and terminate cables from MCP
      • Load Conveyor 2 Pusher Servo (last 3.5 meter through drag chain)
      • Key Switch 2
      • Gate Switch 2
    • Route and terminate cables from the Remote Servo Panel
      • Load Conveyor 1 Pusher Servo (last 3.5 meter through drag chain)
    • Tear down for shipping. Organize cables to be palletized with the enclosures.
      • Utilize M12 QD connections to pull back sensor and actuator cables.
        • Pull back to closest Junction Box or Operator Panel
      • As needed, some cables may not need to be disconnected based on delineation for mechanical unit teardown.
    • Determine and pull multi-conductor cables to the MCP
      • Junction Boxes and Operator Panel
    • Determine and pull the 3phase cables back to the MCP
    • Disconnect and pull the servo cables to their respective enclosure
    Install for Commissioning – West Jefferson, OH
    • Final Drop and termination for the MCP Feeder conductors
    • Customer will supply conduit for the system. 1-1.5” conduit anticipated, to be determined before installation.
    • The installer shall provide the appropriate Fittings, Tees, Hole Seals, Flex Conduit to complete the installation.
    • The installer shall mount conduit to fence, floor, or equipment as specified by the customer
    • Servo power cables shall be run through conduit. Flex conduit shall be used for the final 48” run using a cable gland. Support the flex conduit. The servo is terminated with a connector and does not have threads for accepting conduit fittings.
    • Three-phase power to the Hydraulic Power Unit and the Remote Servo Panel shall be run through conduit. Flex conduit can be used for the final 48” run.
    • Re-route and terminate the cables from teardown.
    • Route and terminate cables associated with each of the 3rd party lathes
    • Process Interlocks Cables
    • Safety Interlock Cables
    • Ethernet Cables
    • CNC Machine Door Switch
    • 1 electrician 1 day (up to 8 hours) to support I/O checkout and debug
#J-18808-Ljbffr
To View & Apply for jobs on this site that accept applications from your location or country, tap the button below to make a Search.
(If this job is in fact in your jurisdiction, then you may be using a Proxy or VPN to access this site, and to progress further, you should change your connectivity to another mobile device or PC).
 
 
 
Search for further Jobs Here:
(Try combinations for better Results! Or enter less keywords for broader Results)
Location
Increase/decrease your Search Radius (miles)
0
200
Filters
Education Level
Experience Level (years)
Posted in last:
Salary